jump to navigation

Progress Report! – The end is near! May 22, 2006

Posted by cmoney in Production Schedule, The All-Stars, Uncategorized.
trackback

Goal Status:

  • C: Cutscene Animations. Start Screen/Presentation slide Art. Any additional Animations
  • D: Finalize Programming. Flesh out First Floor
  • P: Minigame Art, Minigame Testing.
  • R: Help Dave w Programming, Room art
  • L: Minor Animations, Presentation Prep. 

Weeky Percentages:

Chris: 24%

Dave: 26%

Lang: 24%

Russel: 5%

Phil: 21%